The decisions listed in this section have been adopted as complements to market analyses in order to specify the obligations of Proximus regarding the unbundling of the copper local loop. Most of these decisions regard the implementation of the reference offer developed within this framework by Proximus and historically known under the name “BRUO”.
Decisions linked to the market analysis of 29 June 2018
The following decisions have been adopted or are being adopted following the market analysis of 29 June 2018:
- Decision fo 25 March 2020 on the reference offer of Proximus for the unbundled access and bitstream xDSL
- Decision of 30 june 2020 on the revision of the “one-time fees” and the monthly fee for the “ISLA repair”
- Decision of 25 October 2022 regarding the revision of SLA’s and compensation calculation of the BRUO, Bitstream xDSL and Bitstream GPON reference offers of Proximus
In 2021 BIPT has begun the review of this market analysis. In July 2022, the BIPT assessed the evolution of the broadband and TV markets since 2018.
Decisions linked to the market analysis of 1 July 2011
The following decision was adopted following the market analysis of 1 July 2011:
Decisions linked to the market analysis of 10 January 2008
The following decisions were adopted following the market analysis of 10 January 2008:
- Decision of 11 June 2008 – BROBA and BRUO: NTP process
- Decision of 25 June 2008 – Collocation tariffs
- Decisions of 29 November 2006, 6 June 2007 and 2 July 2008 – BRUO: tariff blocks and tie cables
- Decision of 19 November 2008 – BROBA and BRUO: migrations (annex K)
- Decision of 3 August 2010 – BRUO rental fee
- Communication of 8 February 2011 – BRUO and BROBA: Audit of the operational processes of Belgacom
- Decision of 11 August 2011 – BRUO, BROBA, WBA and BROTSoLL: miscellaneous amendments (open calendar, certified technicians, BROBA Ethernet Dedicated VLAN, etc.)
Before 2008
Before the implementation of the system of market analyses, the regulatory framework for the unbundling of the local loop was mainly established by the decisions and opinions on the BRUO interconnection offer of Belgacom, listed below.
- 21 November 2007 – Decision on forecasting and SLA
- 7 November 2007 – Decision on the RE ADSL2 technology
- 4 September 2007 – Decision on the LLU inquiry tool
- 4 September 2007 – Decision on the one-time fees
- 4 July 2007 – Decision on tariffs for splitters
- 13 June 2007 – Decision on the BRUO monthly fee
- 23 May 2007 – Decision on the service quality indicators for BRUO and BROBA
- 24 April 2007 – Decision on an addendum to the BRUO offer
- 4 October 2006 – Decision on the SNA process for the 2006 BRUO offer
- 11 August 2006 – Decision on mass migration forecasting
- 8 August 2006 – Decision on the definition of migration volumes
- 19 June 2006 – Decision on the introduction of ADSL2+ (annex M) within the framework of the BRUO offer
- 13 March 2006 – Decision on tie cables (BRUO 2006)
- 13 February 2006 – Decision on the power upgrades (BRUO 2006)
- 22 December 2005 – Decision on the amendments to the 2006 BRUO offer
- 9 November 2005 – Decision on the 2006 BRUO offer
- 29 August 2005 – Decision on the 2005 BRUO offer (extended SDSL)
- 4 May 2005 – Decision on the 2005 BRUO offer (ADSL2)
- 12 November 2004 – Decision on the 2005 BRUO offer
- 26 October 2004 – Decision on the improved SLA)
- 31 August 2004 – Decision on the 2004 BRUO offer and the trouble ticket first time use
- 31 August 2004 – Decision on tariffs for tie cables and splitters
- 23 December 2003 – Decision on the 2004 BRUO offer
- 9 January 2003 – Opinion on the 2003 BRUO offer
- 6 February 2002 – Additions to the opinion on the BRUO 2002 offer of 12 December 2001
- 12 December 2001 – Opinion on the 2002 BRUO offer
- 2 October 2001 – Addition to the opinion on the 2001 BRUO offer regarding the provision of backhaul lines
- 31 May 2001 – Opinion on the blocks & tie cables
- 27 April 2001 – Opinion on the tariffs of Belgacom for unbundled access (shared access)
- 13 March 2001 – Opinion on the Belgacom tariffs for unbundled access (raw copper)
- 28 February 2001 – Opinion on BRUO 2001 and co-mingling